By Sara Orr, Jennifer Roy and Francesca Bochner

On December 14, 2016, the US Fish and Wildlife Service (FWS) finalized its proposed revisions to the Eagle Rule (Final Rule) and released its Record of Decision (ROD). The Final Rule allows companies and others to obtain 30-year incidental take permits under the Bald and Golden Eagle Protection Act of 1940 (the Act) in exchange for committing to conservation measures designed to reduce impacts to eagles.

As discussed in our previous articles (here and here), this is FWS’ second attempt at revising the Eagle Rule to allow for 30-year permit terms. The draft version of the revisions and the Draft Programmatic Environmental Impact Statement (DPEIS) were originally released on May 2, 2016. FWS accepted public comments on the proposed revisions and DPEIS until July 5, 2016, receiving over 700 comments from other agencies, public interest groups, industry organizations, and private citizens.

By Sara Orr, Jennifer Roy and Francesca Bochner

On July 5, 2016, the public comment period closed for the US Fish and Wildlife Service’s (FWS) proposed revisions to the rules authorizing eagle take permits under the Bald and Golden Eagle Protection Act (Eagle Act) and accompanying Draft Programmatic Environmental Impact Statement (PEIS), paving the way for FWS to complete and release a final rule, possibly as early as the end of this year.

FWS originally released the revised proposed rules on May 6, 2016, as discussed more fully in our previous post. FWS received over 700 comments on the proposed revisions and Draft PEIS from other agencies, public interest groups, industry organizations, and private citizens.

By Joshua Bledsoe, Sara Orr and Stacey VanBelleghem

On August 2, 2016, the White House Council on Environmental Quality (CEQ) issued its final guidance for federal agencies to assess the impact of their decisions on greenhouse gas emissions (GHGs) and also how such decisions may be impacted by a changing climate (e.g., future sea level rise impacts on a long-term infrastructure project proposed for a coastal barrier island) when conducting reviews under the National Environmental Policy Act (NEPA). The final guidance follows CEQ’s issuance of draft guidance in 2010 and revised draft guidance in 2014, incorporating consideration of public comments and feedback on the two drafts. Following this six-year process, CEQ’s guidance is a recommendation to federal agencies versus a formal legal requirement and therefore does not have the same authority as a federal rule or regulation.

The guidance does not establish any particular quantity of GHG emissions as representing a significant burden on the environment – that determination will be left to the discretion of the agencies. However, the guidance does prohibit the so-called “de minimis approach” where an agency would compare a Federal action’s GHG emissions to global GHG emissions, finding that since the action did not represent a meaningful percentage of the global GHG inventory, the action did not significantly affect the environment.

By Sara Orr and Bobbi-Jo Dobush

On July 7, 2016, the US Fish and Wildlife Service (FWS) announced its Record of Decision (ROD) for the Upper Great Plains Wind Energy Programmatic Environmental Impact Statement (PEIS).[1] This is the final step in a process that US FWS, along with Western Area Power Administration (Western), embarked upon in 2010 to streamline the environmental review process for wind energy projects in the Upper Great Plains (UPG).[2] The process applies to wind energy projects in Iowa, Minnesota, Montana, Nebraska, North Dakota, and South Dakota that would interconnect to Western’s transmission facilities or require the US FWS to consider an easement exchange to accommodate placement of project facilities.

Western, which is responsible for marketing and delivering wholesale power in the western United States and is the joint lead agency on the PEIS, announced its ROD adopting Alternative 1 on August 26, 2015.[3] Eleven months later, US FWS made its final decision and also adopted Alternative 1 of the PEIS which supports US FWS participation in easement exchanges for wind development and provides for expedited environmental reviews (including review pursuant to the National Environmental Policy Act (NEPA) and Endangered Species Act (ESA)) if developers follow specified best management practices, minimization and mitigation measures. Now that US FWS has issued its Record of Decision, it may implement the PEIS when permitting wind energy projects involving easement swaps within Western’s Upper Great Plains region.

By Christopher Garrett, Daniel Brunton and Taiga Takahashi

On June 6, 2016, in Backcountry Against Dumps et al. v. Jewell et al., the US Court of Appeals for the Ninth Circuit affirmed the judgment of the District Court for the Southern District of California upholding federal approvals for the Tule Wind Project. The Court of Appeals found in favor of the Federal Government and Tule Wind LLC, rejecting claims the plaintiffs brought under the Administrative Procedure Act, National Environmental Policy Act (NEPA), Migratory Bird Treaty Act (Bird Act) and Bald and Golden Eagle Protection Act (Eagle Act).

As we have noted in previous reports, project challengers have increasingly alleged, in litigation, that the mere potential to incidentally affect migratory birds requires government agencies and/or project developers to obtain a permit under the Bird Act and the Eagle Act as a precondition to any regulatory approval for the project. The Court of Appeals, like the District Court, rejected this tactic.

By Sara Orr, Jennifer Roy and Francesca Bochner

On May 2, 2016, the US Fish & Wildlife Service (FWS) announced its second attempt to revise its rules authorizing eagle take permits under the Bald and Golden Eagle Protection Act (Eagle Act). The rule would extend the maximum eagle take permit term from 5 to 30 years to better correspond to the typical lifetime of major projects. The proposed revisions are intended to provide clarity on eagle permit regulation, improve permit implementation and increase regulatory compliance while providing strong protection for eagles. Public comments are due by July 5, 2016.

The Bald and Golden Eagle Act

The Eagle Act (16 USC 668-668d) was enacted in 1940 to prohibit the take of bald and golden eagles, except pursuant to federal regulations. The Eagle Act allows the Secretary of the Interior to issue regulations authorizing “take” of eagles for various purposes, with potentially significant fines for violations. Such take must be “compatible with the preservation of bald or golden eagles.” The current “preservation standard” is that the take must be “consistent with the goal of maintaining stable or increasing breeding populations.”

Authors: Sara Orr and Jennifer Roy

On August 11, 2015, the US District Court for the Northern District of California remanded a US Fish & Wildlife Service’s (FWS) 2013 final rule that had extended the maximum duration of eagle take programmatic permits under the Bald and Golden Eagle Protection Act (Eagle Act) from 5 years to 30 years.[i] FWS promulgated the rule (an amendment to the existing eagle permitting program established in 2009) to align the duration of programmatic eagle take permits with the typical lifetime of renewable energy projects, such as wind farms. Bird protection groups then challenged the rule, alleging the FWS did not properly comply with the procedural requirements of the National Environmental Policy Act (NEPA) and the Endangered Species Act. While the district court recognized that “promoting renewable energy projects may well by a ‘worthy goal,” the court held that FWS did not meet its procedural obligations under NEPA and remanded the matter back to the FWS to complete the necessary environmental review. As a result of the Court’s decision, 30-year incidental take permits are no longer available to project developers under the Eagle Act until the FWS completes its environmental review and reissues the rule.

The Eagle Act’s Regulatory Scheme

The Eagle Act prohibits a person from taking, possessing, purchasing, bartering, offering to sell, transporting, exporting or importing bald or golden eagles, whether the eagle is alive or dead, or “any part, nest, or egg” of an eagle without a permit.[ii] Under the Eagle Act, take includes to “pursue, shoot, shoot at, poison, wound, kill, capture, collect, molest, or disturb.”[iii] “Disturb” is further defined broadly by regulation, including agitating or bothering a bald or golden eagle “to a degree that causes, or is likely to cause injury to an eagle, a decrease in its productivity, or nest abandonment, by substantially interfering with normal breeding, feeding, or sheltering behavior.”[iv] The federal government can assess both civil and criminal penalties for unauthorized take of bald and golden eagles.[v]

By Marc Campopiano, Joshua Bledsoe, Jennifer Roy, James Erselius

Phase I of the Desert Renewable Energy Conservation Plan (“DRECP”) is underway on the 9.8 million acres of public land managed by the Bureau of Land Management (“BLM”). As discussed in our previous post, the four lead agencies responsible for the plan introduced a phased approach to implementing the DRECP in March 2015 in response to public comments. Under Phase I of this approach, between 81,000 and…

By Andrea Hogan and Joshua Marnitz

On May 6, 2015, the US Senate Committee on Homeland Security and Governmental Affairs voted 12-1 in favor of a bill designed to streamline the Federal permitting process for major energy and infrastructure projects. The bill, first introduced in January 2015 by Senators Rob Portman (R-Ohio) and Claire McCaskill (D-Missouri) as S. 280 or the Federal Permitting Improvement Act of 2015, will now proceed to the full U.S. Senate for consideration.

If passed, the…

By Joshua T. Bledsoe and Stacey L. VanBelleghem

On December 18, 2014, the White House Council on Environmental Quality (CEQ) released revised draft guidance on the consideration of greenhouse gas (GHG) emissions and climate change in National Environmental Policy Act (NEPA) review.[1]  The CEQ previously issued this guidance in draft form in February 2010.[2]  Rather than finalize that draft, the CEQ opted to issue significantly revised draft guidance and open a 60-day public comment period, which closes on…