Deadlines for environmental review and new limits on CEQA litigation would apply to qualifying projects, including certain pending proceedings and lawsuits.

By Nikki Buffa, Jennifer Roy, Lucas Quass, and John Detrich

Under the California Environmental Quality Act (CEQA), state and local agencies must, before deciding whether to approve a discretionary project, evaluate and publicly disclose its potential environmental effects and reduce any significant effects where feasible. When a project may have a significant impact, the agency must prepare a detailed Environmental Impact Report (EIR). Once a project is approved, opponents can challenge the agency’s CEQA compliance in court, and if a court finds a deficiency, it currently has wide latitude to halt the entire project until the agency cures the problem. Since its enactment in 1970, CEQA has become one of the most significant laws governing development in California, shaping the timing, cost, and risk of projects throughout the state. As a result, CEQA has been a recurring focus of legislative reform, with lawmakers adopting numerous targeted exemptions and streamlining measures over the decades. Proposition 45 (Prop 45) represents the latest, and potentially one of the most far-reaching, of these efforts.

Prop 45, titled the “Building an Affordable California Act,” is a ballot initiative that, if approved by voters, would establish new deadlines for environmental review, narrow the scope of CEQA litigation, and limit the remedies available to courts for certain “essential projects,” including certain housing projects, clean energy projects, education facilities, and more. Under Prop 45, streamlined review and approval of such projects would be declared a matter of statewide concern, and the state would occupy the field in this area. The measure’s stated purposes include making California more affordable by streamlining and speeding approval of essential projects while maintaining environmental protections.

If a majority of voters approve Prop 45, it would take effect within weeks of the election (specifically, on the fifth day after the Secretary of State files the statement of the vote) and would reach not only new applications but also agency proceedings and lawsuits already underway. Prop 45 would not exempt essential projects from environmental review at either the state or local level, nor reduce an agency’s authority to approve or disapprove them. Use of the new procedures generally would be voluntary: applicants could elect to use none, some, or all of the measure’s provisions, subject to certain mandatory tribal consultation and labor requirements for projects that utilize the chapter. Applicants with pending applications that have not received final approval could withdraw and resubmit them to proceed under Prop 45. Given its potential effects on project timelines, agency processes, public input, environmental analysis, and CEQA litigation, Prop 45 warrants attention from public agencies and private project applicants alike. This article highlights the provisions likely to matter most in practice and considers potential implications.

Overview of Prop 45 Requirements

Prop 45 would set up a new CEQA and permitting framework for designated essential projects, a broadly defined group spanning eight categories, subject to specified eligibility criteria and exclusions: housing, clean energy, water, public health, public safety (including first responder facilities and wildfire risk reduction), broadband internet access, education facilities, and transportation projects. Prop 45 would not exempt these projects from CEQA outright. Rather, it would provide them with distinct review procedures, deadlines, and standards for judicial review. Applicants with qualifying projects could choose to use all, some, or none of these new processes and standards. Prop 45 would also apply to the related infrastructure needed to serve essential projects, such as utility, water, and transportation improvements.

Essential projects would be subject to specified labor standards, with separate standards for housing projects.

Review Timelines

Prop 45 would set timelines for public agency review of essential projects under CEQA. Agencies would have 30 days from receipt of an essential project application to determine whether the application is complete. If the agency does not make a determination within 30 days, the application will be deemed complete. Lead agencies will be required to decide on the appropriate level of CEQA review within 30 business days of the application completeness date. Measured from the application completeness date, the lead agency would have 365 business days to decide whether to certify an EIR, 180 business days to decide whether to adopt a negative declaration or mitigated negative declaration, and 90 business days to determine that a project is exempt or was previously evaluated. The applicant could extend such deadlines upon written request.

If an agency misses one of these environmental review deadlines, the applicant could request a meeting or hearing, which the agency would have to hold within 60 days of the request and at which it would have to approve or disapprove the project. The lead agency would also be required to complete all environmental review documentation or assemble available environmental review documentation within the same 60-day window. Compliance with these deadlines would be a mandatory, nondiscretionary duty, and the applicant could bring a lawsuit within 90 days if the agency fails to act, denies the project, or imposes unlawful conditions of approval. Separate deadlines would apply to other required permits and approvals. For example, a lead agency would generally have to decide any other approvals at the same time as its CEQA determination, and other agencies would generally have to decide within 90 days after the application for their approval is complete or one day after the lead agency approves the project — whichever is later.

Environmental Review Requirements

Prop 45 would also change how environmental review of essential projects is conducted. These changes include:

  • A new early screening and consultation process for all essential projects to identify and protect tribal cultural resources, with consultation limited to federally recognized tribes that are traditionally and culturally affiliated with the project area
  • Public comment periods fixed at 20 days for negative declarations and mitigated negative declarations and 45 days for draft EIRs and subsequent or supplemental EIRs
  • Specified limitations on the timing of comments that may be included in the administrative record, together with restrictions on reopening public comment after a continued hearing
  • Evaluation of impacts based on compliance with laws in effect when the application was submitted, with limited exceptions for certain life-safety requirements and updates to the California Building Standards Code
  • For applicants that complete an optional scoping process, the alternatives analysis in an EIR would be limited to the project, one applicant-proposed alternative, and the no project alternative

Judicial Review

Prop 45 would impose new limits on CEQA litigation against essential projects. Challenges would have to be filed within 30 days of the agency’s notice of determination or exemption and generally resolved within 270 days, including appeals pursuant to existing judicial streamlining procedures applicable to environmental leadership development projects set forth inPublic Resources Code Section 21185. However, a court would be able to extend this deadline by up to 90 days, and the measure would also allow parties to agree to further extensions in writing. CEQA claims would be limited to noncompliance with objective existing laws.

If a court finds noncompliance, the court must issue a writ of mandate identifying the deficiency and the part, phase, or activity it affects. The court could bar work only on that part, phase, or activity until the agency corrects the deficiency, and could not order the agency to rescind its approval. The writ would not reach any part, phase, or activity outside the deficiency identified, and those portions could not be subject to further judicial challenges under CEQA. These judicial review provisions would also apply to lawsuits pending on Prop 45’s effective date.

Practical Implications

Agencies reviewing essential projects may need to revisit how they handle completeness determinations, environmental review schedules, public comment, and the administrative record, as well as how they defend CEQA litigation.

For developers and project applicants, Prop 45 would create an optional streamlining pathway, offering the potential for more predictable timelines and circumscribed CEQA litigation risk. Applicants would first need to confirm that a project qualifies as an essential project, then decide which of the measure’s procedures to use, if any. That choice could shape the scope of environmental review and alternatives analysis, the project schedule, the opportunities for public input, and the project’s exposure to litigation.

Latham & Watkins will continue to monitor developments in this space.